FARMO RES - F.D.22/S - Production line for suppositories and ovules
LeilãoVendedor verificado
Licitação¹ sem IVA
Diretamente ao vendedor
20.000 €
1 / 1
Dados técnicos
· ID 170537328Máquinas
- Licitação¹ sem IVA
- 20.000 € (netto)
- Preço base
- 20.000 € (sem IVA)
- Fim do leilão
- O leilão termina em 16.12.2026 – 15:12 CET.
- Localização
- 77230 THIEUX
¹ Último estado comunicado; prevalecem as informações da leiloeira.
Identifikation
Número do artigo697b7ca6-f2e1-44b4-847e-f4e75e889f0e
Technik
Quantidade1
Descrição
Production line for suppositories and suppositories in PVC, PVDC, PVC + PE, and aluminum strips.
The working procedure requires 2 coils that are aligned to be welded and honeycombed in the forming station.
The alveoli are then ruffled at the bottom and pre-cut.
Then the cells pass under the dosing station to be filled.
After filling, the sockets are cut into strips of 28 or 30 suppositories, to obtain suppositories in 4, 5, 6, or 7 depending on the socket pitch and spacer.
The strips then enter the cooling tunnel, which solidifies the product.
At the exit, the strips enter the thermosoldering station where they are soldered, sealed, and coded before being uncoiled at the top.
Finally, the strips are cut into segments according to the desired quantity.
The line consists of 3 elements: the cell forming block and filling, the cooling tunnel, and the upper welding and cutting station.
It is possible to plan an electrical and electronic upgrade with a new PLC and a touchscreen for line control for an additional €9500
Sold without the cooling unit, but we can provide one extra.
Maximum production rate: 27,000/h.
Total power: 12Kw
Rated power consumption: 8 kW
Power supply 380 V
Pneumatic energy: 1200 L/minute.
Line clearance dimensions: 7.20 x 2.50 x 2.20m
Auction-ID: A1-53321-124
The working procedure requires 2 coils that are aligned to be welded and honeycombed in the forming station.
The alveoli are then ruffled at the bottom and pre-cut.
Then the cells pass under the dosing station to be filled.
After filling, the sockets are cut into strips of 28 or 30 suppositories, to obtain suppositories in 4, 5, 6, or 7 depending on the socket pitch and spacer.
The strips then enter the cooling tunnel, which solidifies the product.
At the exit, the strips enter the thermosoldering station where they are soldered, sealed, and coded before being uncoiled at the top.
Finally, the strips are cut into segments according to the desired quantity.
The line consists of 3 elements: the cell forming block and filling, the cooling tunnel, and the upper welding and cutting station.
It is possible to plan an electrical and electronic upgrade with a new PLC and a touchscreen for line control for an additional €9500
Sold without the cooling unit, but we can provide one extra.
Maximum production rate: 27,000/h.
Total power: 12Kw
Rated power consumption: 8 kW
Power supply 380 V
Pneumatic energy: 1200 L/minute.
Line clearance dimensions: 7.20 x 2.50 x 2.20m
Auction-ID: A1-53321-124